Research and analysis

Low voltage network capacity study

A research study of unconventional options for expanding the capacity of the low voltage (LV) electricity distribution network to meet demand in 2050.

Documents

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email [email protected]. Please tell us what format you need. It will help us if you say what assistive technology you use.

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email [email protected]. Please tell us what format you need. It will help us if you say what assistive technology you use.

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email [email protected]. Please tell us what format you need. It will help us if you say what assistive technology you use.

Details

»Ê¹ÚÌåÓýapp Low Voltage Network Capacity Study aimed to identify and evaluate the potential of unconventional options for expanding network capacity to meet forecast electricity demand in 2050 at lower cost than conventional reinforcement.

Phase 1 was a qualitative assessment of all options for increasing capacity, resulting in a ranked list of nearly 30 options from which a shortlist of 8 was recommended for quantitative assessment in Phase 2.

In Phase 2, the shortlisted options from Phase 1 were modelled using the EA Technology ’� techno-economic model to see if they could lower the cost of expanding network capacity compared with conventional reinforcement and with existing ‘smart� options such as flexibility and smart charging.

Phase 2 found that 3 shortlisted options could contribute significantly to further lowering network reinforcement costs by several billion pounds by 2050, these being:

  • network data monitoring
  • phase balancing
  • behind-the-meter battery storage

In the Phase 2 Extension report, battery storage was further analysed to establish its value to the network as a function of the location of the storage and to what extent the network benefits could cover the full cost if purchased by the customer.

»Ê¹ÚÌåÓýapp study by supported by was funded by the BEIS Net Zero Innovation Portfolio (NZIP). It was undertaken from May 2021 to March 2022, and is referred to in the Electricity Networks Strategic Framework.

Updates to this page

Published 4 August 2022