Littlehampton Arun East Bank flood risk management scheme

Updated 30 November 2017

Background

皇冠体育app Environment Agency, working in partnership with Arun District Council, West Sussex County Council and Littlehampton Harbour Board, carried out improvements to the tidal flood defences along the East Bank of the River Arun in Littlehampton between 2013 and 2015. 皇冠体育app work was done by contractors, Volker Stevin.

皇冠体育app scheme improved flood defences from the lighthouse on the Promenade to north of the A259. It raised the height of flood defences on the east bank from Arun Parade near the mouth of the River Arun, through the town centre to north of the A259.

Latest update: November 2017

When the Littlehampton East Bank scheme was completed in 2015, one section of tidal wall along the river frontage of 47 River Road was not completed as part of the original scheme as it was expected that it would be delivered as part of a private development. This did not happen so the Environment Agency has stepped in to replace this section of aging flood defence. Work is due to start on 29 November 2017 and finish by January 2018 (subject to weather conditions).

Construction

皇冠体育app work required to replace the existing flood defence will include a new vertical sheet steel pile flood defence wall. 皇冠体育app new flood defence wall will be 26 metres long and will be installed on the riverward side of the existing timber retaining structure. 皇冠体育app steel sheet piles will be installed from a jack-up barge on the River Arun. 皇冠体育app wall will meet the alignment and height of the adjacent walls upstream and downstream of the area. Concrete capping beams will be put in place and connected to the existing downstream walls to form a water-tight connection.

皇冠体育app barge needs to be as close to the current wall as possible in order to carry out the work safely. 皇冠体育app Environment Agency has contacted pontoon holders and users to agree the relocation of their floating pontoon along with any vessels. 皇冠体育appse will need to be moved away from the immediate construction area in order to allow the appropriate space required for this work.

You may notice noise during this work. 皇冠体育app duration of the piling work will be approximately 2 weeks and piling is planned to be completed by mid-December 2017. 皇冠体育app installation of the steel sheet piles will result in increased noise levels locally. 皇冠体育app Environment Agency will take steps to minimise this and will also aim to complete piling activities as quickly as possible. 皇冠体育app contractors will be working from 7am to 6pm weekdays and from 8am to 1pm on Saturdays. Piling will not start until after 9am.

Contingency plans

皇冠体育app Environment Agency has robust contingency plans in place to use temporary defences during bad weather and high tides until the works are complete. 皇冠体育app 拢22-million scheme is nearly finished and is already performing as it should to reduce tidal flood risk to 拢188,500,000 worth of homes, businesses, and other property in the district.