Notice
Full details of auction parameters and interconnector de-rating factors
Published 18 July 2022
Table 1: Auction parameters
T-1 Auction for delivery in 2023/24 | T-4 Auction for delivery in 2026/27 | |
---|---|---|
Target capacity | 5.8GW | 42.4GW |
Demand curve: minimum capacity at price cap | 4.8GW | 40.9GW |
Demand curve: maximum capacity at £0 | 6.8GW | 43.9GW |
Reliability Standard | 3 hours LOLE | 3 hours LOLE |
Net CONE | £49/°ì°Â/²â°ù | £49/°ì°Â/²â°ù |
Price Cap | £75/°ì°Â/²â°ù | £75/°ì°Â/²â°ù |
Price Taker Threshold | £25/°ì°Â/²â°ù | £25/°ì°Â/²â°ù |
15-year agreement threshold | N/A | £295/°ì°Â |
3-year agreement threshold | N/A | £150/°ì°Â |
Indexation | N/A | 2021/22 |
Table 2: Interconnector de-rating factors
Interconnector | Connection capacity (GW)[footnote 1] | T-1 auction 2023/24 Delivery Year [footnote 2] NG:ESO range (%) |
T-1 auction 2023/24 Delivery Year Recommended DRF (%) |
T-4 auction 2026/27 Delivery Year NG:ESO range (%) |
T-4 auction 2026/27 Delivery Year Recommended DRF (%) |
---|---|---|---|---|---|
IFA (France) |
2 | - | - | 30-97 | 63 |
IFA2 (France) |
1.1 | - | - | 30-97 | 65 |
ElecLink (France) |
1 | - | - | 30-97 | 69 |
BritNed (Netherlands) |
1.2 | - | - | 51-92 | 61 |
Moyle (Northern Ireland) |
0.5 | - | - | 14-94 | 54 |
EWIC (Republic of Ireland) |
0.5 | - | - | 14-94 | 54 |
NemoLink (Belgium) |
1 | - | - | 31-95 | 64 |
NSL (Norway) |
1.4 | - | - | 84-100 | 83 |
VikingLink (Denmark) |
1.5 | - | - | 48-91 | 55 |