Press release

Report 02/2015 Derailment at Stoke Lane Level Crossing

RAIB has today released its report into the derailment of a freight train at Stoke Lane Level Crossing, near Nottingham 27 August 2013.

Distorted rail and crossing surface at derailment site Stoke Lane Level Crossing

Distorted rail and crossing surface at derailment site Stoke Lane Level Crossing

Summary

On 27 August 2013, at around 04:27 hrs, a freight train comprising a Class 66 locomotive and 30 fully loaded tank wagons carrying diesel fuel, derailed by two axles as it traversed Stoke Lane level crossing on the Newark to Nottingham line. 皇冠体育app train was travelling at a speed of 53 mph (85 km/h) when the trailing wheelsets of the 26th and 28th wagons derailed. Consequential damage to the rear of the train resulted in an air leak and the automatic application of the brakes. 皇冠体育app train came to a stop after around 1.3 km, at Carlton station. 皇冠体育app wagons remained upright and in line, and did not foul the adjacent running line. 皇冠体育appre was no leakage of diesel fuel from any of the tank wagons. 皇冠体育app track was damaged by the derailed wheelsets for a distance of around 800 metres. 皇冠体育app driver was not injured. 皇冠体育app railway remained closed for repairs until 15:30 hrs on 8 September 2013.

皇冠体育app immediate cause of the derailment was a severe dip in the track which developed rapidly under the leading portion of the train. After the derailment, severe dips of about 100 mm were found in both rails of the affected line, where the rails had deformed over a large void in the ground which had left the track unsupported over a length of around 3 metres. 皇冠体育app void under the railway and other voids found later under the adjacent road surface were caused by excessive ground loss during the recent construction of a microtunnel along the road centre line. RAIB鈥檚 investigation has interpreted the available evidence in order to identify the most likely cause of the voids. Although some alternative explanations cannot be completely discounted, RAIB considers that the most likely explanation for the ground loss is that it was as a result of overmining of the ground during the construction work.

Recommendations

皇冠体育app RAIB鈥檚 investigation identified safety lessons, both for those in the construction industry who build undertrack crossings and also for the railway regarding managing asset protection processes for such constructions. In line with the RAIB鈥檚 remit, the improvement of railway asset protection processes to prevent recurrence has been the focus of its investigation. This is reflected in the balance of the recommendations made, which relate to the following areas:

  • disseminating key learning points arising from this accident to the UK tunnelling industry, via the Health and Safety Executive and relevant industry bodies
  • improving Network Rail鈥檚 asset protection standard for construction of under track crossings so that there is one unified standard applicable to both outside parties and Network Rail
  • improving the technical knowledge of Network Rail鈥檚 asset protection engineers about under track crossings and increasing the time and technical assistance available to them to adequately assess risks and review documentation submitted by outside parties and
  • reviewing the suitability of the action limits in Network Rail鈥檚 standard for monitoring track movement over or adjacent to civil engineering works, including under track crossings

Notes to editors

  1. 皇冠体育app sole purpose of RAIB investigations is to prevent future accidents and incidents and improve railway safety. RAIB does not establish blame, liability or carry out prosecutions.

  2. RAIB operates, as far as possible, in an open and transparent manner. While our investigations are completely independent of the railway industry, we do maintain close liaison with railway companies and if we discover matters that may affect the safety of the railway, we make sure that information about them is circulated to the right people as soon as possible, and certainly long before publication of our final report.

  3. For media enquiries, please call 020 7944 3108.

Newsdate: 2 April 2015

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email [email protected]. Please tell us what format you need. It will help us if you say what assistive technology you use.

Updates to this page

Published 2 April 2015